05-16-2018, 11:49 AM
(05-15-2018, 08:48 PM)tllim Wrote:(05-15-2018, 01:46 PM)Rustproof Wrote:Pending on the 8-layer PCB delivery time.(05-14-2018, 11:30 PM)tllim Wrote:(05-14-2018, 09:09 AM)Rustproof Wrote:(05-12-2018, 03:07 PM)tllim Wrote: Sorry that in general we don't reveal production quantity.I understand... Would it be possible to send in money to reserve a RockPro64 ahead of production?
PINE64 operates in organic growth path and don't accept investment, this allows us to participate with PINE64 community and not need to get influence by investor decision. Since not need to chase on money trace for investor and low operating cost, this allows PINE64 operate in slim profit margin and pass this benefit to community.
BY saying so, this means that we produces enough quantity base on limited cash flow we have in hand, but not large enough to flood the whole market.
This would will help solve the cash flow and the fulfillment for the growing community.
Thanks, still have enough cash flow to sustain ROCKPro64 production :-)
Not to worry, the second batch is a big lot and should able to supply for 1-2 months.
Thank you for the reassurance. Are we still on track for early to mid-June?
Great!